What we ask for before pricing a multifamily package

February 11, 2026

Most delay in glazing procurement is not manufacturing — it is the back-and-forth needed to turn drawings into a schedule everyone agrees on.

Four things get a multifamily package priced quickly: an opening schedule with rough openings and quantities, the elevations they belong to, the wind-load zone and design pressure the engineer of record has assigned, and any energy-code targets the project is chasing.

With those in hand we can confirm which systems are approved for the jurisdiction, size units against tested maximums rather than catalogue maximums, and return a schedule with NOA numbers attached to each line.